Where the grid jabbers.
Shared observations. Local control. Verified transitions.
Explore the architecture ↓

Where the grid jabbers: Envi.Base controllers turn local observations into a shared picture of the grid. Each controller measures and manages demand and generation only within its own home or business. Neighbours exchange status and available flexibility, while each installation retains authority over its own assets.

Three complementary communication layers keep information moving: 5G provides the wide-area backbone; LoRa mesh carries compact messages between reachable radio peers; PLC mesh relays data over usable power conductors. Eligible nodes are distributed across KPN, Vodafone and Odido where coverage and provisioned profiles allow, reducing dependence on one mobile network.

Controllers build a shared picture by comparing voltage changes over time, matching phases and exchanging timestamped observations. A sudden loss of voltage or PLC neighbours can be reported through a surviving radio or mobile route. These observations identify a candidate fault region; they do not establish electrical isolation.

The design goal is to keep safe, authorized switching available across a wide range of single-path failures. A surviving validated route can preserve coordination and external permission signals, so losing one communication layer need not prevent a transition. Availability remains conditional on powered equipment, reachable peers and valid, fresh evidence.

Grid-forming starts only when any damaged span is excluded, separation is externally verified, protection is ready, supply is adequate and operator authorization is valid. A suitable inverter then establishes the island reference; Envi.Base adjusts only its own assets. When these conditions cannot be verified, the system blocks the transition or follows its engineered shutdown policy.

Envi.Base Grid Edition · Communication architecture

Where the
grid jabbers.

Three rings. One coordinated grid.
5G to the cloud. LoRa mesh between neighbours. Powerline along the cables. Controllers share what they see, relay what matters and build a common picture. Each box manages demand and generation only within its own home or business.

Technical explainer · October 2026 · Interactive reference architecture
Three complementary communication layers around the local Envi.Base controller: 5G, LoRa mesh and powerline.01 / 5G02 / LoRa mesh03 / PowerlineWIDE AREALOCAL RADIOCABLE NETWORKCOMPLEMENTARY PATHS. LOCAL AUTHORITY.
Distributed control architecture FIG. 01
THE CONTROL BOUNDARY

One box.
One home or business.

Control inside the premises

Each Envi.Base measures and manages demand and generation within its own installation. Only connected, controllable assets can be adjusted.

Coordinate beyond it

Peers exchange measurements, available flexibility and proposals. Each peer decides and acts locally. Feeder switching, island-wide protection and authorization remain with the responsible external systems and operator.

01 / THE COMMUNICATION STRATEGYThree logical layers, not three literal ring networks

Different paths.
Shared information.

The grid jabbers through compact, purposeful messages: who is reachable, what changed and which observations agree. Each medium carries what it does well; essential messages can take another validated route.

01 / WIDE AREA

5G as the backbone

5G provides the wide-area IP backbone. Eligible controllers use different mobile operators; local mesh links let an offline node forward compact messages through a peer with a working cloud path.

Carries
Telemetry, schedules, logs, updates
Depends on
Coverage, operator, backhaul & cloud

Cellular service may degrade during a power outage. 5G is a proposed upgrade; the current Envi.Base documentation specifies a mobile modem, not a 5G capability. [1, 2]

02 / LOCAL RADIO

What is LoRa mesh?

LoRa is a long-range, low-data-rate radio. A mesh protocol lets powered peers forward small packets over multiple hops, selecting an alternate reachable relay when a route fails. Local radio can cross an open electrical boundary.

Carries
Health, alarms, compact state summaries
Depends on
Radio reach, relays, airtime & backup power

Routing adds hop limits, duplicate suppression and path health. Standard LoRaWAN uses gateways; it is not the peer mesh described here. [3]

03 / CABLE NETWORK

What is PLC mesh?

PLC sends data over power cables. In a PLC mesh, reachable modems relay packets along the remaining conductors. The routing graph can change with noise and switching. A broken span cannot be repaired by routing over that same span.

Carries
Local telemetry, beacons, phase evidence
Depends on
Coupling, noise, cable & switch configuration

PLC phase-identification timing supports discovery. Hearing a modem is not proof of a shared feeder or phase: signals can couple across conductors. G3 PLC/RF hybrid routing is not automatically a LoRa mesh. [4, 5]

The goal is continuity through diverse paths. Availability still depends on power, coverage and valid routes. Three interfaces cannot guarantee that communication always works; local control must also handle losing all three.

02 / TRY THE FAILOVER

Lose a link.
Keep a defined response.

Switch the paths on and off. This schematic assumes reachable, powered endpoints and a working relay when a path is enabled.

5G backboneLoRa meshPLC meshElectrical connectionUnavailable data path
Transformer, two feeders, three phases and six Envi.Base controllersA transformer supplies feeders F01 and F02. Each feeder has L1, L2 and L3 conductors. Six separate premises exchange data through PLC, LoRa mesh and diverse 5G operators.DISTRIBUTION TRANSFORMERMV → LV / 3-phaseF01 · CANDIDATE DOWNSTREAM GROUPF02 · INDEPENDENT FEEDERTX-01L1L1L2L2L3L3Envi.Cloud backboneKPN / VODAFONE / ODIDOE1 · L1–L3 / Company AKPNE2 · L2 / Home BVodafoneE3 · L3 / Home COdidoE4 · L1 / Company DKPNE5 · L2 / Home EVodafoneE6 · L3 / Home FOdidoS1S2CONCEPTUAL FEEDER MAP · SOLID: ELECTRICAL CONDUCTORSDASHED: COMMUNICATION OVERLAYS
PLC cable segmentSCROLL MAP ↔3 / 3 paths available
03 / 5G BACKBONE & CARRIER DIVERSITY

Different operators.
Shared situational awareness.

Six sites use the three Dutch mobile networks: KPN, Vodafone and Odido. Diversity is planned across eligible profiles and actual local coverage—not SIM brand names. [9, 10]

Spread. A persistent commissioning policy balances reachable operators across neighbours. Use network identity, coverage, permitted profiles and stable device-ID tie-breaks; add dwell time and hysteresis to avoid everyone moving at once.

Hint. A node reports attach status, cloud-probe failures, power health and timestamps over reachable LoRa or PLC paths. Independent reports can suggest a carrier-path impairment; one timeout cannot diagnose an operator-wide outage.

Recover. Relay compact traffic through a healthy peer first. Switch only eligible, already provisioned profiles using tested local fallback. A new eSIM profile cannot be assumed available during an outage.

SIMULATE A MOBILE-NETWORK IMPAIRMENT
5G backboneLoRa meshPLC meshElectrical connectionUnavailable data path
6 direct cloud paths

Independent operator paths are available.

Select an operator to impair its modeled path.

The three communication toggles in the network lab apply here too. Local PLC relays remain within reachable cable fragments; LoRa can link the two feeders. Losing 5G end-to-end connectivity does not identify which operator, backhaul or cloud component failed. Physical infrastructure can share failure causes.

04 / CABLE FAULT → COORDINATED RESPONSEReference scenario · no live plant connected

Detect the change.
Protect the boundary.

An excavator damages F01. Controllers compare local measurements and reachable peer reports. Grid-forming is enabled only after external equipment excludes the damaged span from the island.

NORMAL / GRID CONNECTEDTX-01 / F01 + F02 / L1 · L2 · L3
5G backboneLoRa meshPLC meshElectrical connectionUnavailable data path
Transformer, two feeders, three phases and six Envi.Base controllersA transformer supplies feeders F01 and F02. Each feeder has L1, L2 and L3 conductors. Six separate premises exchange data through PLC, LoRa mesh and diverse 5G operators.DISTRIBUTION TRANSFORMERMV → LV / 3-phaseF01 · CANDIDATE DOWNSTREAM GROUPF02 · INDEPENDENT FEEDERTX-01L1L1L2L2L3L3Envi.Cloud backboneKPN / VODAFONE / ODIDOE1 · L1–L3 / Company AKPNE2 · L2 / Home BVodafoneE3 · L3 / Home COdidoE4 · L1 / Company DKPNE5 · L2 / Home EVodafoneE6 · L3 / Home FOdidoDAMAGED SPANS1S2CONCEPTUAL FEEDER MAP · SOLID: ELECTRICAL CONDUCTORSDASHED: COMMUNICATION OVERLAYS
Utility supplies both feedersMAP ↔

What the devices detect. Loss of voltage, changed phase observations and lost PLC neighbours. Correlated reports identify a candidate cable segment; the devices do not see an excavator or prove that a conductor is safely isolated.

What permits supply restoration. S1 and S2 open around the fault. Valid external isolation, protection and authority exclude the damaged span. A’s own suitable three-phase inverter can then form the downstream island; B and C retain local control. F02 stays separate.

05 / WHICH FEEDER? WHICH PHASE?

A radio neighbour
is not an electrical neighbour.

A feeder is an outgoing distribution circuit. A phase is L1, L2 or L3. Keep both separate from the communication network.

01

Start with a commissioned map

Register device, transformer, feeder, phase reference and switch boundaries. The operator-approved map defines which devices may coordinate an island.

02

Discover, then corroborate

Exchange authenticated feeder beacons over PLC. Combine neighbours and voltage-event correlation with the map and switch telemetry. A beacon or similar voltage alone cannot establish membership.

03

Measure phase at the source

Compare same-polarity zero crossings against a known phase reference, using modem-timed PLC frames or sufficiently synchronized clocks. At 50 Hz, 120° is about 6.67 ms. Packet arrival time over radio is unsuitable. [4]

04

Revalidate after a change

Version the topology and attach freshness and measurement quality. Switching, poor timing or conflicting evidence makes the affected assignment uncertain until checked again.

TOPOLOGY EXAMPLESILLUSTRATIVE
REFERENCE NODEA / L1Commissioned reference
OBSERVED NODEA / L1Map + timed phase evidence
Phase relationship exampleTwo measurements on feeder A, phase L1, show approximately zero phase difference against a commissioned reference.0 ms10 ms20 ms
Δφ ≈ 0°Same phase relationship

Both nodes are assigned to feeder A / L1. The observed phase relationship supports the commissioned phase label; it does not prove that every switch between them is closed.

Same angle does not mean same feeder. Grid-connected feeders may be synchronized. PLC can couple across conductors; its reception does not mean phases are electrically tied. Never connect L1, L2 and L3 together to extend communication.

Membership is not isolation. Even a good feeder map needs fresh boundary-switch feedback, interlocks and a protection design before island energization.

06 / OBSERVE THE CABLE NEIGHBOURHOOD OVER TIME

Watch the voltage.
Match the phase.

A single voltage value says little. Correlated local changes over a longer window, timed phase measurements and a commissioned map build a stronger picture together.

SYNTHETIC VOLTAGE HISTORY · ONE-MINUTE SAMPLES · SCROLL CHART ↔
E1 / L2E2 / L2
Voltage comparison over the selected observation periodSynthetic data shows voltage changes at two controllers over time.
VOLTAGE CHANGE CORRELATION—

Correlation of one-minute voltage changes after subtracting the matching transformer-phase reference. This removes a shared upstream component; it does not prove a shared cable.

INDEPENDENT PHASE MATCHΔφ ≈ 0°

Phase offset comes from synchronized high-resolution or modem-timed measurements—not minute averages or radio packet arrival times.

OBSERVATION RESULT

Candidate cable neighbourhood

Compare the traces across a longer window.

120 changes observed

Same phase, different feeder. Select E5: phase still matches, but local voltage changes follow a different pattern. Shared upstream disturbances can also create misleading correlation.

Evidence, not a switching permit. Cable impedance, local load, PV, neutral effects and sensor errors influence the signal. Confidence requires calibrated field validation, topology records and switch evidence. [12] The score here is descriptive—not a calibrated probability.

07 / GRID-FORMING POWER LABState machine + active-power balance · reference scenario

Local assets.
Explicit island-entry gates.

One company and two homes in an operator-approved island. Each Envi.Base controls only its own premises. A suitable inverter at company A provides the voltage reference. [7, 8]

Model boundary

A supervised start, local load reduction, reserve depletion and a blocked restart. It does not calculate three-phase stability, reactive power, fault currents or protection coordination, and cannot establish electrical safety.

YOUR PREMISES / COMPANY AControl stops at your connection.

Example hardware: 20 kWh storage; 15 kW discharge, 10 kW charge; 20% reserve floor. Illustrative values, not Envi.Base ratings or protection settings.

External evidence & local readiness

These are simulated inputs from the responsible equipment or parties. Envi.Base A cannot establish feeder-wide facts from its own meter.

GRID CONNECTEDReference: utility grid
5G backboneLoRa meshPLC meshElectrical connectionUnavailable data path
Peer coordination routePLC mesh
Three premises, separate control boundariesCompany A controls only its own loads, solar and battery. Homes B and C have their own controllers. An external operator controls the grid boundary. ? Utility gridEXTERNAL BOUNDARYCLOSED · OPERATOR EQUIPMENTOperator/protection equipment suppliesisolation evidence. Envi.Base does not switch it.COMPANY A · YOUR PREMISESHOME B · PEERHOME C · PEER Envi.Base AEnvi.Base BEnvi.Base CDemand 10 / solar 4 kWNet demand 2 kWNet demand 2 kWOwn battery + GFM inverterGrid-forming disabledOwn assets controlled by BOwn assets controlled by CReported state · no actuation from AReported state · no actuation from ALOCAL ACTUATION ONLYPEER MODEL · FIXED EXTERNAL INPUTPEER MODEL · FIXED EXTERNAL INPUT DATA: PLC MESH · STATUS / PROPOSALSPOWER FLOWS ACCORDING TO THE ELECTRICAL NETWORK
Own flexible load reduced0 kW
Own battery output / input0 kW
Ideal time to reserve—
The grid supplies the balance. No controller has direct control over a neighbour’s demand.
Return is break-before-make: the local source is stopped first. No live parallel closing or seamless transfer is simulated.
Sequence log 0 simulated min
  1. INITIAL Grid connected. Local source not grid-forming.

The example assumes both homes follow the island reference, no other forming source, a verified total load envelope and authorized export from A. Peer demand is external context—not a control input for Envi.Base A. The communication switches above also apply here; this conservative demo stops shared-island supply on total link loss. Real hardware needs independently engineered protection and a site-specific loss-of-communication policy.

08 / WHAT FLOWS THROUGH THE RINGS?

Small state messages.
Selective detail.

The application chooses priority and payload. The link budget determines frequency—especially on a shared radio mesh.

InformationProposed transport policyPayload / timing approach
Health & external boundary evidenceOwn health, externally confirmed switch position, alarms, permission freshnessCompact on any validated path; selected duplicationTens of application bytes; event-driven plus budgeted heartbeats
Coordination summariesOwn available power, reserve, mode, per-phase measurements; peer-reported commitmentsPLC / 5G normally; reduced summaries on meshTypically tens to hundreds of bytes; slow down when capacity falls
Discovery evidenceFeeder beacon, phase offset, quality, map versionPLC measurements; results can travel on any pathOn join, on change and during scheduled revalidation
Logs & firmwareDetailed history, diagnostics, signed software updates5G preferred; pause during degraded operationKilobytes to megabytes; never crowd out essential status
Fast protectionTrips, electrical interlocks, voltage / frequency controlLocal protection and engineered local interfacesNo dependency on cloud or best-effort mesh delivery

Count airtime, not just bytes.

LoRa trades data rate for range. Hops, headers, authentication, acknowledgments and retries all consume capacity. PLC also needs field measurement; 5G capacity depends on the selected modem and service. No link rate is guaranteed here. [3, 5, 6]

Planning example: 48 bytes of application summary per node. The calculation excludes all protocol overhead and is not a radio feasibility test.

EXPLORE THE MESSAGE LOAD
256 bit/sAggregate payload carried across all hops

20 × 48 bytes × 8 × 2 hops ÷ 60 seconds

Not the load on every radio. Check the busiest relay, time on air, sub-band access rules and retry headroom separately.
09 / ONE APPLICATION CONTRACT

Change the route.
Keep the meaning.

Transport redundancy only helps when every received message has the same identity, freshness and authority.

WHO & WHEREDevice + group

Authenticated device ID, commissioned feeder / phase assignment, evidence quality and topology version.

WHEN & WHICHTime + sequence

Sample timestamp, clock quality, boot/session ID, sequence number and expiry. Old status becomes unknown.

WHAT & WHO MAY ACTState + authority

Measured state, command ID, coordinator epoch and permission validity. A command acknowledgment is not switch feedback.

Route by health and priority. Use a common authenticated message envelope over IP, PLC and the selected mesh stack. Deduplicate repeated messages; expire delayed commands and queue history separately.

A network split must not create two leaders. Use a defined coordinator and fenced authority with expiry. A coordinator sends proposals, not direct neighbour actuation. Each premises retains its own limits. Missing operator authority blocks new island transitions.

10 / BUILDING THE GRID CONTROL EDITION

Communication diversity.
Local control authority.

Keep actuation inside each premises. Add coordination interfaces and integrate externally supplied grid-boundary evidence.

01

Add the interfaces

Select 5G hardware, a LoRa mesh stack and phase-aware PLC. Back up local controllers and communication relays; external parties must also maintain boundary-status equipment.

02

Build the control layer

Add topology evidence, route health, message expiry and coordinator fencing. Use external boundary feedback; interface only with the own installation’s suitable inverter and controllable loads.

03

Validate the failure matrix

Test every link combination, relay loss, shared power failure, stale status, incorrect phase labels, partitions and restoration with the operator.

ISLAND ENTRY GATE

Verified boundary separation + ready protection + adequate supply + valid operator authorization → island mode

On grid return: retain isolation until operator release, synchronization checks and closing interlocks pass. Three communication paths do not replace these gates. [7]
PILOT / SUGGESTED PARTS LISTThree nodes · Proposed components · October 2026

Make the conversation
tangible.

A starting bill of materials for three Envi.Base locations. Begin on a controlled test network, then move to an approved field installation. These are component candidates, not a validated, ready-to-install Grid Edition kit.

Front view of the Envi.Base enclosure
One controller. Three communication paths. Per location.

Each node combines an Envi.Base, a LoRa radio, a PLC interface, a 5G router and a three-phase meter. The controller manages only the assets within its own premises.

3 × LOCAL NODES
Suggested hardware quantities for a three-node communication and discovery pilot
FunctionTotal quantitySuggested componentPilot integration / selection note
LOCAL CONTROLEnergy controller31 per locationEnvitron Envi.Base ↗

Local demand, generation and device coordination; Ethernet / Modbus and supported device drivers.

Confirm firmware access, meter drivers and the interface for peer messages with Envitron. External LoRa, PLC and 5G adapters require integration; their combined operation is not an existing capability claim.
LoRa MESHLocal radio3 kitsOptional 4th relayRAKwireless WisMesh RAK4631 starter kit ↗

EU868 variant, RAK19007 base, antenna and enclosure. A practical platform for short peer messages.

Use a controlled Meshtastic proof of concept or purpose-built mesh firmware. Add the serial adapter / service that bridges messages to Envi.Base. Measure airtime, retries and relay behavior; this is not a protection channel.
PLC MESHPowerline interface3 setsBoard + host per nodeMicrochip PL460-EK · EV13L63A ↗

With a compatible host, such as SAME70 Xplained, G3-PLC firmware and a host-to-controller bridge.

Controlled laboratory evaluation only. The board is not a finished field modem. Confirm host revision, permitted PLC band and coupling arrangement. A field pilot needs an enclosed, suitably approved modem and engineered phase coupling. Manufacturer restrictions ↗
5G BACKBONEMobile gateway3 routers6 SIMs / subscriptionsTeltonika RUTX50 ↗

EU-compatible 5G router, dual SIM, Ethernet and the required cellular antennas.

Spread primary subscriptions across KPN, Vodafone and Odido; use an independent secondary carrier per router. Confirm coverage and contract access. Dual SIM switches between subscriptions; it does not provide two simultaneous cellular links. Peer hints and coordinated carrier selection need pilot software.
MEASUREMENTThree-phase meter3 meters+ 9 matched CTsSiemens SENTRON PAC4220 ↗

Modbus TCP; class 0.2S active-energy metering. Select matched 1 A / 5 A current transformers for each phase.

Log per-phase RMS voltage, current and power with timestamps for voltage-correlation studies. CT accuracy and installation affect system accuracy. Energy accuracy is not a phase-timing specification; ordinary Modbus polling does not deliver synchronized waveforms.
PHASE REFERENCESynchronized recording2 setsRent for pairwise testsSchneider Electric PowerLogic ION9000 ↗

Waveform-capable reference meters with matched sensors and an engineered GPS / PTP time source.

Compare two nodes at a time; add a third recorder for simultaneous three-node tests. Validate waveform timestamp alignment, export access and clock-quality flags. Published 1 ms timing corresponds to 18° at 50 Hz per device; it does not establish precision synchronization for reconnection.
POWER & INSTALLATIONKeep the node alive3 setsSize after load measurementPhoenix Contact QUINT4 DC UPS family ↗

Compatible PSU, UPS controller and battery, plus voltage conversion where needed, enclosures, Ethernet and interface cables.

Match every device's supply voltage and isolation requirements. Size backup for the entire measurement and communication chain, not just Envi.Base. Include the meter supply, PLC host, router and any relay that must report after power loss.
THE SOFTWARE WORK PACKAGE

The parts need a common language.

Budget for device adapters, authenticated peer identities, a compact message format, sequence numbers, timestamps, expiry, deduplication, store-and-forward and route health. Provide one isolated pilot logging service with local buffering at all three nodes. These integration tasks are part of the pilot.

IF THE PILOT ALSO FORMS AN ISLAND

Add a separate power test package.

The list above tests communication and discovery. Actual grid-forming also needs a suitable inverter and battery, controllable loads, rated isolation hardware with verified position feedback, independently engineered protection and local interlocks. Include synchronization checks for any permitted reconnection and operator authorization for the agreed test boundary.

First acceptance test

Observe a known phase assignment, disable one data path at a time and record message delivery, loss and recovery. Simulate a cable break with approved test switching. Verify that uncertain isolation blocks grid-forming. Add a transformer-side reference node only with the network operator's permission.

Suggested engineering shortlist, checked against manufacturer documentation on 27 October 2026. Quantities assume three three-phase locations; final variants, integration, availability and pricing require supplier confirmation. Hardware purchase alone does not validate the architecture.

Scope of this whitepaper

Each Envi.Base controls only demand and generation within its own premises. Grid-forming requires a suitable inverter within the premises and independently engineered external protection. This proposed architecture does not claim current support for all three communication interfaces. Feeder and phase examples are illustrative. Mesh routing, payload budgets, timing accuracy and protection behavior require site-specific design and testing.

Technical sources ↗
  1. Envitron · Current Envi.Base and mobile connection
  2. GSMA · Mobile networks during power loss
  3. LoRa Alliance · Standard LoRaWAN architecture; research · LoRa peer-to-peer mesh
  4. Microchip · PLC phase identification and zero crossings
  5. G3 Alliance · PLC integration guidance; Microchip · Noise and coupling limitations
  6. Semtech · LoRa physical data rates
  7. NREL / Sandia · Intentional island requirements (US-oriented technical background, not local grid approval)
  8. NLR · Grid-forming inverters and microgrid control
  9. RDI · The three Dutch mobile network operators
  10. GSMA · IoT remote SIM provisioning
  11. G3 Alliance · PLC / RF mesh routing
  12. Watson · Smart-meter voltage correlation for distribution topology, with known limitations